This photo shows an extra 10-feet tower section that was added to the top to allow the system to reach two overhead cranes that sat on a higher set of travel rails. This extension was removed once each piece was lowered, allowing a remaining overhead crane running on a lower set of travel rails to pick the piece off the lifting beams.